Finland’s Licensing and Supervision Authority ordered Google’s representative to suspend preparatory work at planned data center sites in Muhos and Kajaani until required environmental assessments are completed. The Guardian reported that forest had already been cleared at both sites; Google said it acted in good faith under forestry rules and would follow the authority’s guidance.
Finland’s Licensing and Supervision Authority has ordered Google’s representative to suspend specified preparatory work at planned data center sites in Muhos and Kajaani until environmental impact assessments are completed. The order follows extensive land clearing and other site work before the assessments were finished, raising questions about whether environmental effects were properly identified before construction preparations began.
The authority, known as LVV, said Tuesday that work which significantly changes the environment at the two sites must stop, with the suspension due immediately and no later than October 23. It gave the company until the following Wednesday to provide a written explanation. The assessments are still under way and are expected to be completed later this year, according to The Guardian’s report.
LVV said preparatory work had included tree removal, topsoil stripping and site-road construction. The report said Tuike Finland Oy, the company representing Google, had cleared about 330 hectares in Muhos before completing an assessment. Logging had also reportedly taken place across just under 200 hectares in Kajaani. The source does not establish that a court has found the company acted illegally; the immediate development is an administrative order tied to the unfinished assessments.
Google said it understood the concerns and had “fallen short of our own high standards.” The company said it would study LVV’s findings and follow its guidance, while maintaining that it had acted in good faith under the Forestry Act, conducted nature surveys and taken steps to protect high-value areas. It also cited plans for tree planting across 130 hectares in Muhos as part of its landscaping and biodiversity work.
Environmental Reviews Halt Site Work
The order puts a pause on specified preparations at two sites within a reported €13 billion data center project in northern Finland. It matters because environmental assessments are intended to identify and evaluate potential impacts before major changes are made to a site. LVV’s position, as reported by The Guardian, is that the clearing and other work could affect the environment in ways the assessment process is meant to examine.
The case also highlights a practical tension between rapid data center development and local oversight. Finnish Association for Nature Conservation chief operating officer Tapani Veistola said the situation appeared to reflect a systemic problem, citing intense demand and limited expertise in small municipalities. That is his assessment, not a finding by LVV. If the company does not comply with the order, the authority said it would consider enforcement proceedings and a fine.
environmentally friendly data center construction tools
As an affiliate, we earn on qualifying purchases.
As an affiliate, we earn on qualifying purchases.
How the Finland Sites Reached This Point
The planned facilities in Muhos and Kajaani are part of Google’s wider investment across multiple northern Finland locations, according to the report. The construction push comes amid strong demand for data center capacity to support online infrastructure. That commercial pressure provides context for the pace of work, but does not determine whether legal or environmental requirements were met.
The central issue in LVV’s order is the timing and scope of site preparation relative to the ongoing environmental impact assessments. Google points to surveys and protective measures under the Forestry Act; LVV says the preparatory measures change the environment and can create impacts that should be identified and assessed. The authority’s order is temporary and specific to work it says significantly changes the sites, rather than a reported cancellation of the data center plans.
““In our opinion, the measures in question will change the environment and cause impacts, the identification and assessment of which are among the key objectives of the EIA procedure.””
— Tommi Muilu, head of the environmental department at Finland’s Licensing and Supervision Authority, as quoted by The Guardian
tree planting kits for landscaping
As an affiliate, we earn on qualifying purchases.
As an affiliate, we earn on qualifying purchases.
Legal Findings and Site Impacts
The available report does not say that a court or regulator has made a final finding that Google illegally cleared the land. LVV has issued a temporary suspension order over specified preparations while assessments continue. The full findings of those assessments, and whether they will require changes to the projects, remain unknown.
It is also unclear how much work will be affected in practice, what environmental impacts the completed assessments will identify, and whether the authority will pursue penalties. Google’s position that it acted in good faith under forestry rules has not been resolved in the information provided. The reported cleared areas and planned replanting are separate figures and should not be treated as offsetting one another without further evidence.
As an affiliate, we earn on qualifying purchases.
Written Response and Assessment Results
Google’s representative was asked to submit a written explanation by the deadline stated by LVV. The company has said it will study the authority’s findings and follow its guidance. The specified preparatory work is to be suspended by October 23 at the latest, while the assessments are expected to finish later in the year.
LVV said it may consider enforcement proceedings and a fine if the company does not comply. The next key developments are the authority’s response to Google’s explanation and the completed environmental assessments, which should clarify the effects identified and whether additional restrictions or project changes are required.
environmental impact assessment guide
As an affiliate, we earn on qualifying purchases.
As an affiliate, we earn on qualifying purchases.
Key Questions
Did Finland order Google to stop all construction?
No. LVV ordered a suspension of preparatory measures that significantly change the environment at the Muhos and Kajaani sites while assessments are completed. The report does not describe a cancellation of the projects or a blanket halt to all activity.
Why did the authority issue the order?
LVV said significant site work, including tree removal, topsoil stripping and road construction, was under way before the environmental impact assessments were complete. The authority said assessing potential impacts is a key purpose of that process.
How much forest was cleared?
The Guardian reported that about 330 hectares had been cleared in Muhos and that logging had taken place across just under 200 hectares in Kajaani. These are reported site figures; the supplied material does not provide a final official accounting of forest loss.
Has Google been found to have acted illegally?
The supplied report describes an administrative order related to unfinished environmental assessments, not a final court ruling that Google acted illegally. Google said it acted in good faith under the Forestry Act, and the issue remains subject to the authority’s review.
What happens next?
Google’s representative must provide a written explanation by the deadline set by LVV, and the specified work must be suspended by October 23 at the latest. The environmental assessments are expected later in the year; LVV said it could consider enforcement action and a fine if the order is not followed.